Construction insolvency is not a new problem. With the continued presence of fixed price contracts, in an industry which has always been troubled with cash flow problems and low profit margins, coupled with persistent cost inflation and labour and materials issues affecting the supply chain, it is no surprise that we continue to see insolvencies. The question is, what can you do to protect yourself from insolvency?
Here the court refused to grant an injunction restraining contractor Space from presenting a winding up petition against the employer COD. The employer had failed to pay 3 applications for payment (nos.
In another case involving a winding-up petition, the petition was dismissed, after the court found there was a dispute as to whether the statutory payment scheme applied to the contract. The contractual arrangements between the parties were not formally documented, but there was a basic agreement as to the scope and price of the works, which arose out of a subcontract between Ro-Bal and main contractor McAlpines to provide fabrication and erection of steelworks at two sites. At one site the works were completed and paid for, but at the other there was a dispute regarding payment
Here the Court of Appeal granted an injunction which restrained a building contractor (Harbour View) from presenting a winding-up petition, overturning the high court's decision at first instance. Harbour View had been engaged under two separate contracts based on a JCT Intermediate WCD (2011) to carry out works at two separate sites. The employer (Wilson) failed to pay against two interim certificates (August 2013 and September 2013), leaving a sum of over GBP 1.6 million owing.
Here the court refused to grant an injunction restraining contractor Space from presenting a winding up petition against the employer COD. The employer had failed to pay 3 applications for payment (nos.
Here the Court of Appeal granted an injunction which restrained a building contractor (Harbour View) from presenting a winding-up petition, overturning the high court's decision at first instance. Harbour View had been engaged under two separate contracts based on a JCT Intermediate WCD (2011) to carry out works at two separate sites. The employer (Wilson) failed to pay against two interim certificates (August 2013 and September 2013), leaving a sum of over GBP 1.6 million owing.